02. 07. 2019

How to set a rolling date for Project Publishing Date?

It is possible to set rolling dates on different locations in Quant. The advantage is that there is no need to keep an eye on whether they are up to date because they are keeping up to date on their own. An example of such use may be the rolling date of the Project Publishing Date which you want to keep in the future.

In the project properties, you can set that the date should be always, for example, the first day of next month instead of a fixed date.

Thanks to this setting, you won't have to manually reset the Project Publishing Date when it is in the past and simultaneously a warning message that the publishing date of the project is in the past won't be displayed every time you open a project.